Tsyrkuny sits just across the ring road from Kharkiv's Pivnichna Saltivka, and that closeness to the city cost the village almost everything: the oblast Recovery Service puts destruction at 80%. The same closeness, now to the front line, is why the large-scale rebuild there has still not begun, even though Tsyrkuny is one of six settlements the government selected for comprehensive recovery under the "build back better" principle. Here is what the state concept sets out for the village, what it costs and why the works are stalled.
How Tsyrkuny entered the state recovery programme
The government's intent was set out by Denys Shmyhal, Prime Minister at the time: "they will rebuild not individual buildings and structures, but everything – with a systemic approach, new planning and a full transformation of these settlements". The same statement gave the principle its name: "Build back better".
The list in the annex to the resolution is short.
| Settlement | Oblast |
|---|---|
| Borodianka, urban-type settlement | Kyiv |
| Moshchun, village | Kyiv |
| Posad-Pokrovske, village | Kherson |
| Trostianets, town | Sumy |
| Tsyrkuny, village | Kharkiv |
| Yahidne, village | Chernihiv |
In the summer of 2023 the Kharkiv Oblast Military Administration proposed replacing Tsyrkuny with Staryi Saltiv because of constant shelling. The government did not support the swap, and the village stayed on the list.
What the concept of comprehensive recovery sets out for the village
Andrii Aleksieiev, head of the Service for Recovery and Infrastructure Development of Kharkiv Oblast, described the approach this way: "We developed a concept of comprehensive recovery – we took a broader view than our colleagues, because we have the time for it".
This is a rebuild of the village, not repairs to individual houses: it starts with what lies underground and ends with landscaping.
- Utilities go underground. Power lines and the water main are laid in the ground: debris does not tear them, and losses are lower.
- New roads and buildings. Administrative premises and housing are designed from scratch rather than patched.
- Renewable energy. The concept includes a solar power plant and wind turbines.
- Public spaces. A landscape park and a recreation area by the water body.
- Dormitories for people who come to work or to start a business in the village.
From the outset the Recovery Service allowed that not all of the concept would be delivered: "we are reducing some stages or removing them altogether", if the state decides that such capital investment is not justified.
Why capital works are on hold
"The recovery of the settlement of Tsyrkuny is on hold right now for obvious reasons. Because it is practically impossible to work there", Andrii Aleksieiev explained in January 2025. The works were suspended after the situation in the north of Kharkiv oblast escalated.
What has already been done
- The built-up area went through land release. The certificates confirming that the survey was complete were signed by Mykola Sikalenko, head of the military administration, on 3 August 2023.
- Power supply has been restored. That took almost a year; the grid was raised from nothing.
- Design work continues, including for the underground utilities.
The scale of the works depends on one more thing. The Recovery Service does not hide it: before billions are invested, it needs to know how many people will return once hostilities end.
What is happening in the village instead of the large-scale rebuild
- A modular outpatient clinic operates in Tsyrkuny, installed with support from international donors.
- Drinking water is delivered to residents by truck.
- Generators and shelters are being put in place.
We cover two things here: electricity and water. We handed generators over to the hromada, and in 2025 we assessed what needs to change in water supply and wastewater: we went to the site, ran field surveys and laboratory tests.
How exactly we did that is in the piece on the water systems of Tsyrkunivska hromada.
Which energy programmes are already open to residents
The terms depend on who the borrower is: the owner of a private house or an association of co-owners. In both cases the loan starts from 0% at banks partnered with the "5-7-9%" programme, and the difference lies in the amount, the term and the share of compensation.
| Who | Terms published on 16 February 2026 |
|---|---|
| Owners of private houses and townhouses | Loan from 0% at banks partnered with the "5-7-9%" programme, amount up to UAH 480,000, term up to 10 years. The state compensates up to 30% of the cost of equipment: generators, batteries, solar installations as part of an off-grid system |
| OSBBs (condominium associations of co-owners) and housing construction cooperatives | Loan from 0% at 43 partner banks, amount up to UAH 3 million, term up to 3 years. Compensation of up to 50% of the cost of a generator and up to 70% for a solar power plant or a heat pump |
The three compensation ceilings here are different and do not add up: a private house up to 30%, an OSBB on a generator up to 50%, an OSBB on a solar installation or a heat pump up to 70%.
How this differs from the "Tsyrkuny 2030" Strategy
We separate them by three markers: who drafted the document, what it covers and where the money comes from.
| Concept of comprehensive recovery | "Tsyrkuny 2030" Strategy | |
|---|---|---|
| Who drafted it | The oblast Service for Recovery and Infrastructure Development | A working group of the Tsyrkuny Village Military Administration |
| What it covers | Engineering rebuild of the village: utilities, roads, buildings, energy | Development of the hromada up to 2030, including forests, the river and wetlands |
| Source of funding | The state budget within the experimental project | State programmes, grants, partners, the hromada's own budget |
The details of the Strategy and the fund's role in it are in the article Tsyrkuny 2030: the fund's contribution.
What the fund did not do in this story
- The fund did not draft the concept. Its author is the Service for Recovery and Infrastructure Development of Kharkiv Oblast.
- The fund does not manage the money of the state programme and does not influence the order of facilities within it: that sits at the level of the state and the oblast.
- The fund does not name a start date for capital works. It will be set by the Cabinet of Ministers and the Oblast Military Administration.
- The fund does not confirm the volume of state funding. About UAH 10 billion is the Recovery Service's estimate, not our calculation.
- Resolution of the Cabinet of Ministers of Ukraine No. 382 of 25 April 2023 "On implementing an experimental project on the recovery of settlements…" (version in force as of 20 March 2025)
- Government portal: six settlements designated for comprehensive recovery
- Ukrinform, 21 January 2025: a concept of comprehensive recovery has been developed for the village of Tsyrkuny
- ATN, 12 February 2025: the renovation of Tsyrkuny, what it will cost and when it makes sense to start the works
- Suspilne Kharkiv, 6 August 2023: what stage the government project to rebuild the village has reached
- Ekonomichna Pravda, 16 February 2026: the government is expanding energy support programmes for houses
This material is for information only and is not legal advice. Data on the concept, the timelines and the terms of state programmes are given as of the publication dates in the sources; the terms of energy programmes and decisions on starting the works change, so before you submit documents, check the figures with a partner bank, at the village council and on official resources.
FAQ
Why was Tsyrkuny included in the state programme of comprehensive recovery?
How much does the concept for the recovery of Tsyrkuny cost?
What does the concept of comprehensive recovery of the village set out?
When will capital works in Tsyrkuny begin?
What has already been done in the village?
Is the experimental project running in 2026?
How does the concept of comprehensive recovery differ from the "Tsyrkuny 2030" Strategy?
What is the fund's role in the recovery of Tsyrkuny?
Which energy programmes are open to residents without the large-scale rebuild?
Who decides when capital works will begin?
The key points
Tsyrkuny remains on the list of six settlements under Resolution of the Cabinet of Ministers No. 382, the concept of comprehensive recovery is ready, and capital works are on hold because of the security situation. The decision to start is taken by the government and the Oblast Military Administration.
The hromada is living now, and it needs water, electricity and heat. That is the part the fund covers together with its partners.
Support the work in front-line hromadas: the fund's open fundraisers. Partnership: [email protected].